New Construction Reference · San Francisco, CA

6 Critical Fire Protection Items for Your New Construction Punch List

NFPA 13 §28NFPA 72 §14.4IFC §901.5

Final fire protection acceptance is frequently where new commercial construction projects stall — not because the systems don't work, but because the documentation, labels, or acceptance tests weren't completed. These six items show up on close to every punch list for a reason.

For San Francisco commercial buildings: this guide applies to properties across San Francisco · Bay Area. SF commercial high-rises and Title 24 compliance need specialized expertise. Enforcement is handled by SF Fire Department.

Last updated: 2026-11-08 · Published by Fire Solutions NW · CA C-10 Electrical + C-16 Fire Protection · Licensed in 6 states

1

NFPA 13 Contractor's Material and Test Certificate (Form 28.3.1)

NFPA 13 §28.3.1

The fire sprinkler contractor must complete and submit the NFPA 13 Material and Test Certificate, signed by the installer and a witness. Without this document the AHJ will not sign off on occupancy. Owners rarely know to ask for it.

2

NFPA 72 Record of Completion and 100% Device Test

NFPA 72 §7.5

Fire alarm acceptance requires 100% functional test of every initiating device, notification appliance, and relay, documented on the NFPA 72 Record of Completion. Verify the test was performed by the installer witnessed by the AHJ.

3

As-Built Drawings Delivered to Owner AND AHJ

NFPA 13 §28.3.4

Record drawings showing actual installed sprinkler layout, alarm device locations, and equipment identification must be delivered at completion. Many jurisdictions require a copy posted inside the fire riser room.

4

Hydraulic Nameplate at Each Riser

NFPA 13 §7.1.2

Each sprinkler riser must have a permanent metal nameplate showing design area, density, and hose stream allowance. Missing nameplates = immediate NFPA 25 finding at the first annual inspection.

5

Fire Pump Acceptance Test Documentation (If Applicable)

NFPA 20 §14.2

New fire pumps require a formal acceptance test — flow test at 100%, 150%, and churn — witnessed by the AHJ and documented. Common punch-list miss on buildings that took final occupancy before the test was completed.

6

System Impairment Procedures Posted at Riser

NFPA 25 §15.3

The sprinkler riser room must have posted procedures for system impairment: who to call, central station contact, fire watch procedures. Often skipped on new construction and missed at first inspection.

Bottom line for San Francisco facility managers

New construction fire protection acceptance is a documentation exercise as much as a systems exercise. The building owner who makes these six items a specific closeout checklist — handed to the GC and the fire protection subcontractor at the start — eliminates the usual post-occupancy punch-list fire drill.

If you manage commercial property in San Francisco or nearby (Oakland, San Jose, Daly City), Fire Solutions NW can audit against this list and clear any findings before your next AHJ inspection.

Have a specific question about your San Francisco facility?

We serve commercial buildings across San Francisco · Bay Area. Call us directly — 28+ years in the trade, and we self-perform in CA.